Archive & Records Storage
Pallet Rack Relocation For Storage Company
Location
South Brunswick, NJ
Size
436,000 sq ft · 19,807 pallet positions
Timeline
5 weeks
Client
Clutter / Iron Mountain
1 photos · Click any photo to enlarge
The Project
Full teardown-to-reinstall rack relocation for a national moving and storage company. When the client vacated a facility in Wind Gap, PA, Hammerhead repurposed the existing racking for reinstallation at a 436,000 sq ft building in South Brunswick, NJ, delivering 19,807 pallet positions at four and five levels high in a 36-foot clear warehouse.
The Challenge
Reusing the Wind Gap racking meant engineering and permitting a system built from used materials with no structural calculations available from the original installation. The full package had to be re-engineered for the new building, permitted in South Brunswick, and installed in time for the client's busy end-of-year storage season.
The Outcome
Hammerhead produced new engineering for the relocated system, secured permits, and fielded a large installation crew to hit the deadline. The finished installation delivered 19,807 pallet positions with wire decking and pallet support bars, post and row-end protection, wire guidance for turret trucks, and egress tunnels through the long rack rows. The system passed inspection and was approved for use ahead of the client's peak season, completed in five weeks.
Project Details
- Industry
- Archive & Records Storage
- Location
- South Brunswick, NJ
- Facility Size
- 436,000 sq ft · 19,807 pallet positions
- Timeline
- 5 weeks
- Client
- Clutter / Iron Mountain
Systems Used
Have a Similar Project in Mind?
We scope each project around your facility, your product mix, and your operation. Start with a free consultation.
Call or Text (323) 628-8190 · info@hammerheadws.com